Hostname: page-component-7b7567c8c-jswmv Total loading time: 0 Render date: 2026-11-15T10:47:58.050Z Has data issue: false hasContentIssue false

SOLVENCY II TECHNICAL PROVISIONS FOR GENERAL INSURERS

By the Institute and Faculty of Actuaries General Insurance Reserving Oversight Committee’s working party on Solvency II technical provisions:

Published online by Cambridge University Press:  06 February 2015

Rights & Permissions [Opens in a new window]

Abstract

This paper brings together the work of the GI Solvency II Technical Provisions working party. The working party was formed in 2009 for the primary purpose of raising awareness of Solvency II and the impact it would have on the work that reserving actuaries do. Over the years, the working party’s focus has shifted to exploring and promoting discussion of the many practical issues raised by the requirements and to promoting best practice. To this end, we have developed, presented and discussed many of the ideas contained in this paper at events and forums. However, the size of the subject means that at no one event have we managed to cover all of the areas that the reserving actuary needs to be aware of. This paper brings together our thinking in one place for the first time. We hope experienced practitioners will find it thought provoking, and a useful reference tool. For new practitioners, we hope it helps to get you up-to-speed quickly. Good luck!

Information

Type
Sessional meetings: papers and abstracts of discussions
Copyright
© Institute and Faculty of Actuaries 2015 
Figure 0

Figure 1Simplified Illustration of a Solvency II Balance Sheet

Figure 1

Figure 2Breakdown of the Best Estimate Calculation

Figure 2

Table 1LoD Example

Figure 3

Table 2RAD Example

Figure 4

Figure 3Illustration of Effect with Limited Reinsurance and Small Lags Between Gross and Reinsurance

Figure 5

Figure 4Illustration of Effect with More Significant Reinsurance and Longer Delays from Gross Payments

Figure 6

Table 3Impact of Differences Between the R/I and Gross Payment Patterns: Short-Tail with Limited R/I

Figure 7

Table 4Impact of Differences Between the R/I and Gross Payment Patterns: Short-Tail with Significant R/I

Figure 8

Table 5Impact of Differences Between the R/I and Gross Payment Patterns: Long-Tail with Limited R/I

Figure 9

Table 6Impact of Differences Between the R/I and Gross Payment Patterns: Long-Tail with Significant R/I

Figure 10

Table 7Effect of Simplification on the Allowance for Counterparty Default – Short-Tail

Figure 11

Table 8Effect of Simplification on the Allowance for Counterparty Default – Long-Tail

Figure 12

Figure 5Illustration of the Run-off of the SCRs.1SCRRO – SCR component to be run-off. 2SCRUEE – SCR component relating to unexpired exposures. 3SCRRM – SCR component used to calculate risk margin

Figure 13

Table 9Illustration of the Run-Off of the SCRs

Figure 14

Figure 6Distribution of Deviation from Expected Reserves

Figure 15

Figure 7Distribution of Deviation from Best Estimate Over 1 Year

Figure 16

Table 10Triangle Used for Example

Figure 17

Table 11Projected Reserves and Ultimates

Figure 18

Table 12Projected Best Estimate Reserves

Figure 19

Table 13Projected Lead Diagonal from One Simulation

Figure 20

Table 14Projected Reserves from One Simulation Relative to Best Estimate

Figure 21

Table 15Ratio of SCR at Time 0 to the Best Estimate Reserve at Time 0

Figure 22

Table 16Calculate the Risk Margn

Figure 23

Table 17Simplified Example of the Difference Between GAAP and Solvency II

Figure 24

Table 18Back-Testing Example: Comparison of Actual vs Expected

Figure 25

Figure 8How Uncertainty Might be Shown

Figure 26

Table 19Back-Testing Example: How Paid Expected from Different Methods Could be Combined

Figure 27

Table 20Back-testing Example: Combining Paid and Incurred Based Estimates to Come Up with Expected Paids

Figure 28

Figure 9Observations Verses Expected Using the AYLWA

Figure 29

Table 21Looking for Calendar Year Effects in the Triangles

Figure 30

Figure 10Residual Graphs Before Heteroscedasticity Adjustments

Figure 31

Figure 11Residual Graphs After Heteroscedasticity Adjustments

Figure 32

Figure 12Normality Plots Before and After Heteroscedasticity Adjustments

Figure 33

Table 22Simulated Incremental Values (Mean and Standard Error) by AY and Development Period

Figure 34

Figure 13A Symmetrical Threshold System

Figure 35

Table 23For our Example, Observations in the Percentile Ranges

Figure 36

Table 24Results of the Back-Test: Commercial Auto: expectations based on 31 December 2007, actuals accrued during CY 2008

Figure 37

Figure 14Graphical Display of the Results of the Back-test

Figure 38

Table 25Illustrating How an Automated Back-Test Can Provide Early Warning of Changes to Reserves

Figure 39

Figure 15Plot of Residuals Shows Trend Not Allowed for

Figure 40

Figure 16Plot of Residuals After Changing to a New Model

Figure 41

Table 26Comparison of Bootstrap Results on the Old and New Models

Figure 42

Figure 17Technical Provisions as Proportion of Base Reserve