Some scheduling problems with past sequence dependent setup timesunder the effects of nonlinear deterioration and time-dependent learning

Published online by Cambridge University Press:  27 April 2010

M. Duran Toksarı
Affiliation:
Erciyes University, Engineering Faculty, Industrial Engineering Department, Kayseri, Turkey; dtoksari@erciyes.edu.tr
Daniel Oron
Affiliation:
Econometrics and Business Statistics, The University of Sydney, NSW 2006, Australia.
Ertan Güner
Affiliation:
Gazi University, Engineering and Architecture Faculty, Industrial Engineering Department, Ankara, Turkey.
Get access

Abstract

This paper studies scheduling problems which include a combination of nonlinear job deterioration and a time-dependent learning effect. We use past sequence dependent (p-s-d) setup times, which is first introduced by Koulamas and Kyparisis [Eur. J. Oper. Res.187 (2008) 1045–1049]. They considered a new form of setup times which depend on all already scheduled jobs from the current batch. Job deterioration and learning co-exist in various real life scheduling settings. By the effects of learning and deterioration, we mean that the processing time of a job is defined by increasing function of its execution start time and a function of the total normal processing time of jobs scheduled prior to it. The following objectives are considered: single machine makespan and sum of completion times (square) and the maximum lateness. For the single-machine case, we derive polynomial-time optimal solutions.

Information

Type
Research Article
Copyright
© EDP Sciences, ROADEF, SMAI, 2010

Access options

Get access to the full version of this content by using one of the access options below. (Log in options will check for institutional or personal access. Content may require purchase if you do not have access.)

Article purchase

Temporarily unavailable