Hostname: page-component-74656f9884-6grmk Total loading time: 0 Render date: 2026-11-05T11:16:36.989Z Has data issue: false hasContentIssue false

The Weak Spot of Infrastructure BCA: Cost Overruns in Seven Road and Railway Construction Projects

Published online by Cambridge University Press:  03 August 2022

Jan-Eric Nilsson*
Affiliation:
Department of Transport Economics, Swedish National Road and Transport Research Institute, SE-581 95 Linkoping, Sweden
*
*Corresponding author: e-mail: jan-eric.nilsson@protonmail.com
Rights & Permissions [Opens in a new window]

Abstract

This article describes the process from first proposals in the early 1990s to project completion many years later for seven large Swedish road and railway projects. The purpose is to find reasons for the massive cost overruns as well as explanations for why projects are brought to completion despite much higher costs than when the decision to build was made. Cost overruns are set in an institutional context to highlight the interplay among national, regional, and local policymakers. National investment programs are seen as promises by other parts of society, irrespective of whether project costs increase during the process toward procurement and implementation. Another aspect is that the infrastructure manager’s administrative framework currently makes it impossible to compare costs in contracts with final cost, meaning that there is no institutionalized learning process in place. Design preparations and the estimation of costs for new projects must therefore be done without an understanding of what has been working well in the implementation of previous projects. While Benefit-Cost Analysis (BCA) played no role in the planning of the seven projects, the article sends a stark warning that early cost estimates provide poor input for assessing project rate of return.

Information

Type
Article
Copyright
© The Author(s), 2022. Published by Cambridge University Press on behalf of the Society for Benefit-Cost Analysis
Figure 0

Table 1. The seven projects.

Figure 1

Figure 1. Timeline for project planning and implementation.

Figure 2

Figure 2. Price index changes between 1990 and 2020. Sources: CPI from Statistics Sweden and investment indices from the IM’s home page.

Figure 3

Table 2. The seven projects.

Figure 4

Table 3. Nominal costs (a) at the start of the process, (b) when projects are tendered and (c) final.

Figure 5

Table A1. Two activities of a pavement renewal contract’s quantity list.